1. Obtain the Local Government’s Permit Application
– Permit application should include information about the project scope, project location, and the installer.
2. Develop the Site Plan
– Site plan should show location of major components on the property. The site plan drawing need not be exactly to scale, but it should represent relative location of components at site (see supplied example site plan).
– PV arrays in compliance with IRC fire setback requirements need no separate fire setback requirements. Energy storage in acceptable locations.
Download the Document